Our permits finally came through!

The electric soft service has been put up and approved by the state at the site. Water/sewer has been notified and should be getting us a meter and service soon (6-8 weeks we've been told).

The surveyors came out yesterday and re-marked the house corners.

The all-important (we-won't-work-at-your-site-if-it-isn't-there) "port-a-potty" arrived on site today!

Doggett Co. was out at the site today beginning the process for digging the footings for the house and laying out the basement. Here are some pictures:







Yipppeeee!!!!!

Projected finish date: September 15, 2008.